Pile driving for the North Side Elevated Tank foundation and construction of the elevated tank foundation began on January 4, 2016 and will continue through January 15, 2016.
DPW PROJECT ADVISORY
DPW Project Advisory – North Side Elevated Tank
7516 Hayward Road
Frederick, MD January 7, 2016: Pile driving for the North Side Elevated Tank foundation and construction of the elevated tank foundation began on January 4, 2016 and will continue through January 15, 2016. All work will be performed on the work site at 7516 Hayward Road by Landmark Structures.
No traffic detours are expected, however, citizens should be aware that there will be construction equipment entering and exciting the work site. Motorist should proceed with caution when passing the work site area.
In addition, there will be heavy steel pounding noise during the daylight hours.
For additional information contact: Eugene Chastain, Landmark Structures, at echastain@teamlandmark.com or 1-817-439-8888, X1211.
###